EV charging provision as part of new build planning permission?

Former Community Member
Former Community Member
As per subject, I was asked this morning about the practicalities for EV provision by an electrician. Apparently, it has been stipulated as a condition of granting planning permission for some new build dwellings, so I asked for sight of this.


Whilst it is usual for the planning to seek comments from the water authority for sewage disposal, I doubt if the DNO has been consulted.


Has anyone else come across this?


Regards


BOD
  • Former Community Member
    0 Former Community Member
    OMS:


    I'd imagine that the planners have no interest in consulting with DNO's  - principally as the response isn't likely to be "on message"


    Regards


    OMS




     


    My council seems to consult my DNO for everything including a garage conversion despite having a 3 phase 100A supply (not that the council has that specification)!