BS7671 Amendment 2 transition period on existing projects

My question relates to the latest amendment to the wiring regulations; BS7671:2018:A2:2022 and the transition period on live projects.

I am currently working on multiple large residential projects that have been designed upto Stage 3 and tendered, but will not commence on-site until after the 27/09/22 which is the withdrawal date of AMD 1. The new regulations state that electrical installation commencing after the withdrawal date (27/09/22) must comply with AMD 2. 

We now have an issue of the developer coming back to us shouting about additional costs  due to the addition of AFDDs, which are required as part of AMD 2 but only 'recommended' as part of AMD 1, so have not been included in the original design. 

Has anyone had any issues with this on their projects? As the design is complete and tendered can we not install to AMD 1?