This discussion has been locked.
You can no longer post new replies to this discussion. If you have a question you can start a new discussion

Virtual Commissioning

Former Community Member
Former Community Member
Hello,


​I would be interested to hear the experiences from those who uses virtual commissioning to test PLC code prior to actual commissioning.


​We use a system called WinMOD, where the machine / line is modeled in 3D and to scale. Sensors, safety devices, etc. are added to the model as they would be on the actual line. As the system is to test the completeness and quality of the PLC code, hardware such as VFD's are substituted using macros that replicate the actual functions and connections they are emulating. The PLC I/O is assigned to the emulated hardware and line sensors. Once completed, the PLC is connected to the PC running the 3D model and associated software. An emulated control station & HMI can then be used to run the line, as if it were the actual line.

The PLC / HMI software is tested through normal and abnormal conditions, faults simulated and recovered. Software issues can be resolved and fault recovery simplified. The line can be left running for a number of days to test the robustness of the PLC code. All this prior to the actual commissioning. 

Whilst the VC process can appear to add significant cost to the project, actual commissioning time will be reduced and subsequent downtime from software bugs should be eliminated. If done correctly, a digital start up should be possible, hence achieving an overall cost reduction. VC is not for every automation and controls project, cost analysis is needed to ensure that it is cost effective for the project.

4375c582ab45724a99c974f00e01dd7a-huge-winmod.png

3D Model of a production line.



Kind regards,


Jon
Parents
  • Former Community Member
    0 Former Community Member
    Thanks for the comments ...


    William, for the 3D mechanical model, we cross reference against the plant Catia drawings and use the Eplans to ensure all control components are included on the model and / or emulated. Once the 3D line is up and running under PLC control, we can see if a sensor/s has been missed out of the VC project as an area will behave not as planned. On the package we use, you cannot detect issues such as an underrated VFD but you can test the complete control behavior of the VFD.


    Regards,


    Jon
Reply
  • Former Community Member
    0 Former Community Member
    Thanks for the comments ...


    William, for the 3D mechanical model, we cross reference against the plant Catia drawings and use the Eplans to ensure all control components are included on the model and / or emulated. Once the 3D line is up and running under PLC control, we can see if a sensor/s has been missed out of the VC project as an area will behave not as planned. On the package we use, you cannot detect issues such as an underrated VFD but you can test the complete control behavior of the VFD.


    Regards,


    Jon
Children
No Data