This discussion is locked.
You cannot post a reply to this discussion. If you have a question start a new discussion

The True Cost of Wind Power

Wind power is often sold to us as the ‘cheapest’ option. With the current fossil fuel prices that may be the case, but is the quoted strike price of £40 per kWh really valid?

 

The wind turbine manufacturers appear to be struggling:

https://www.bloomberg.com/news/articles/2022-11-07/wind-giant-rues-promise-that-renewable-power-could-be-free

Manufacturers such as Vestas Wind Systems A/S are seeing losses pile up as orders collapse at a time when they should be capitalizing on the turmoil in natural-gas markets. To blame -- at least in part -- is the industry’s insistence that clean electricity can only get cheaper, according to Henrik Andersen, chief executive officer of the Danish wind giant.

Vestas expects its profit margin to be around -5% in 2022.

“The output from the turbine has never been more valuable,” Andersen said. “But we are losing money in manufacturing a turbine.” Vestas has raised prices more than 30% in the past year to help stem losses.

 

New installations no longer seem to be viable at the agreed prices:

https://newbedfordlight.org/major-massachusetts-offshore-wind-project-no-longer-viable/

A major offshore wind project in the Massachusetts pipeline “is no longer viable and would not be able to move forward” under the terms of contracts filed in May. Both developers behind the state’s next two offshore wind projects are asking state regulators to pause review of the contracts for one month amid price increases, supply shortages and interest rate hikes.

Utility executives working with assistance from the Baker administration last year chose Avangrid’s roughly 1,200-megawatt Commonwealth Wind project and a 400 MW project from Mayflower Wind in the third round of offshore wind procurement to continue the state’s pursuit of establishing cleaner offshore wind power. Contracts, or power purchase agreements (PPAs), for the projects were filed with the Department of Public Utilities in May.

 

I have previously looked at the viability of the Dogger Bank Wind Farm. This is all taken from the official Dogger Bank website:

doggerbank.com/.../

The project is designed in three similar phases but I will just look at one phase:

 

Installed capacity 1.2 GW

Expected annual output 6 TWh

Cost £3 Billion

Strike price £40 per MWh.

Expected Service life not mentioned.

Nameplate output 1.2 x 8760 GWh per year =  10 512 GWh per year = 10.5 TWh per year.

An expected annual output of 6 TWh gives a capacity factor of 57%. Is this realistic?

What will they earn at the strike  price?

6 TWh at £40 per MWh  = £240 Million per year.

Straight payback of £3 Billion in 12.5 years.

 

So with no costs for maintenance, no interest or dividends paid and a very optimistic capacity factor there is a 12.5 year payback on an asset with a 20-25 year lifespan (no one really knows). That is simply not a valid business model. A more realistic strike price is £80-100 per MWh which takes you into the NPP range.

How much of the low strike price has simply been gambling on higher electricity prices and then taking the market rate?

Does anyone have any more encouraging figures?

Parents
  • 12.5 year payback on an asset with a 20-25 year lifespan (no one really knows)

    I doubt that the entire system will need replacing after such a short time - certainly some bits may well - but I suspect much of the structures and infrastructure (e.g. sea bed cables) will be perfectly serviceable for much longer periods. Apparently many north sea oil rigs are still going strong after 40 years.

       - Andy.

Reply
  • 12.5 year payback on an asset with a 20-25 year lifespan (no one really knows)

    I doubt that the entire system will need replacing after such a short time - certainly some bits may well - but I suspect much of the structures and infrastructure (e.g. sea bed cables) will be perfectly serviceable for much longer periods. Apparently many north sea oil rigs are still going strong after 40 years.

       - Andy.

Children
No Data