Why Britain can’t build Nuclear Power Plants

Hinkley Point C is not exactly a standard EPR,

“He said that 70% of equipment had now been delivered for unit 1”, and "many risks are behind us, like the unique British instrument and control system which has been designed and manufactured, with testing under way". He added: "We had to substantially adapt the EPR design to satisfy British regulations, requiring 7000 changes, adding 35% more steel and 25% more concrete. This adaptation and approval process is the same for other developers bringing new designs into Britain. Now the design of our UK plant is complete in detail meaning contractors have certainty over exactly what is needed to build the plant."

https://www.world-nuclear-news.org/Articles/EDF-announces-Hinkley-Point-C-delay-and-big-rise-i

7000 changes, a unique control system, 35% more steel and 25% more concrete. This will be the BS 1363 plug and socket of the nuclear world.