Wind versus Nuclear

The Wind versus Coal thread is getting rather tangled so I will start a new one to look at these points.

The latest Danish 3 GW capacity auction received zero bids:  

https://windeurope.org/newsroom/press-releases/no-offshore-bids-in-denmark-disappointing-but-sadly-not-surprising/

The conditions for this auction were based on the real and full costs of wind power, no subsidies and you pay for the grid connection.

“The Danish auction system does not foresee any form of state support or revenue stabilisation model – such as the Contracts for Difference (CfD) used in many other European countries. Instead offshore wind developers are asked to pay for the right to build a wind farm. Denmark’s uncapped negative bidding creates an unhealthy race to the bottom and unnecessarily increases the upfront costs for offshore wind developers. On top of that Denmark does not pay for the grid connection to the offshore wind farms, instead developers have to take on these extra costs.”

There was a similar story for the 2023 UK auction:

No new offshore wind project contracts have been bought by developers at a key government auction, dealing a blow to the UK's renewable power strategy.

https://www.bbc.com/news/business-66749344

 

Australia is starting to move slowly in the direction of nuclear power although there are deep political divides. A recent study looked at the costs of a renewable solution including costs of grid connection, storage and backups compared to a solution including nuclear.

It notes:

“nuclear generates 38% of electricity with just 13% of total capacity.”

“From an economic cost perspective, the economy is much better off in the Progressive scenario with nuclear power in the energy mix compared to AEMO’s preferred Step Change solution using primarily renewables and storages.”

The numbers seem fair and show the influence of capital versus variable costs for nuclear:

3.2.3 Cost of nuclear power

The modelling assumes a cost of nuclear power of $10,000/kW. This is higher than the CSIRO’s recent estimate of the cost of large-scale reactors.10 This assumption is based on a review of the experience of the costs of developing large scale nuclear reactors, including more recent examples. Further, it is assumed there is an annual cost efficiency improvement in the capital cost of nuclear generators of 1% per annum in these costs from 2024 onwards. This is a conservative estimate based on the literature on the learning cost efficiencies when similar units are developed in sequence. The capital costs are amortised over a 50-year period, although realistically new nuclear generators will operate for many more years than this and more than twice the life of renewables. A real variable cost of $30/MWh is also assumed. This is higher than the expected variable cost of nuclear power. This amount is considered sufficient to cover fuel costs, variable and fixed operating and maintenance cost, network costs and decommissioning costs over the life of the power stations.

https://www.frontier-economics.com.au/wp-content/uploads/2024/12/Report-2-Nuclear-power-analysis-Final-STC.pdf

So which way should we go?

Parents
  • Doing a bit of a rough calculation, those figures suggest that 1MW of nuclear power plant would cost $10,000,000 to build.  Let's say you borrowed money at 4% interest to pay for that.  That gives $400,000 per year per MW.  Divide by 365 and then by 24 gives $45.7 per MWh generated.

    In other words, nuclear power is so expensive to build that the cost of paying the interest on the loan to build the power station could well exceed the cost of actually running the power station, given as £30 per MWh.

    Note that my figure of 4% interest is just an example, not based on anything in particular.

  • We need nuclear and must do everything we can to reduce the building costs to a minimum safe limit and then add a safety factor of 2 to cover unknown future events.

    We already have approved nuclear sites and these should be used for the new nuclear as armed security guards are already well trained in repelling  terrorist attacks.

    No provision should be made for decommissioning as we will always need the sites and could use the army to maintain security even if the site was not in use.

    25GW of nuclear is needed now not in 2050 so we need to revise the Sibert radiation limit by next Christmas

  • That is a little bit simplistic as you are not paying down the principle sum.  I also think they are using Australian dollars which are currently around GBP 0.5. This lowers the numbers somewhat.

    Total generation cost $75.7 per MWh ~£37 per MWh.

    To pay down  $10 million over 40 years (reasonable lifespan?)  is $250 000 per year ~$29 per MWh.

    This takes the total cost to £ 51 per MWh for nuclear.

     

    Doing similar number for wind, taking the published data for Dogger Bank:

    https://doggerbank.com/press-releases/dogger-bank-wind-farm-a-and-b-reaches-financial-close/

    Dogger Bank A

    Installed capacity 1.2 GW

    Cost £3 Billion (including cabling to shore but not beyond)

    Capacity factor 55%

    Cost per MW installed £2.5 million.

    Cost per MW delivered £4.5 million (capacity factor 0.55)

    Using your 4% interest gives £180 000 per year per MW ~ £21 per MWh generated

    To pay down £2.5 million over 20 years is £125 000 per year ~£14 per MWh.

    This takes the total cost to £ 35 per MWh not including maintenance (this appears to be included in the running costs of the nuclear plant).

    What is also not included is the back up or storage systems required when the wind power is not generating, 45% of the time.

Reply
  • That is a little bit simplistic as you are not paying down the principle sum.  I also think they are using Australian dollars which are currently around GBP 0.5. This lowers the numbers somewhat.

    Total generation cost $75.7 per MWh ~£37 per MWh.

    To pay down  $10 million over 40 years (reasonable lifespan?)  is $250 000 per year ~$29 per MWh.

    This takes the total cost to £ 51 per MWh for nuclear.

     

    Doing similar number for wind, taking the published data for Dogger Bank:

    https://doggerbank.com/press-releases/dogger-bank-wind-farm-a-and-b-reaches-financial-close/

    Dogger Bank A

    Installed capacity 1.2 GW

    Cost £3 Billion (including cabling to shore but not beyond)

    Capacity factor 55%

    Cost per MW installed £2.5 million.

    Cost per MW delivered £4.5 million (capacity factor 0.55)

    Using your 4% interest gives £180 000 per year per MW ~ £21 per MWh generated

    To pay down £2.5 million over 20 years is £125 000 per year ~£14 per MWh.

    This takes the total cost to £ 35 per MWh not including maintenance (this appears to be included in the running costs of the nuclear plant).

    What is also not included is the back up or storage systems required when the wind power is not generating, 45% of the time.

Children
No Data