Continued cost overruns for UK based infrastructure projects - Will we ever learn?

Sunday I sat reading the usual crop of the weeks papers and other magazines and journals as I relaxed during the morning and of the articles that I focused on I noticed a common theme emerging, that being the significant cost overruns on HS2 and also Sizewell C.  This led me to fire up the computer and after a couple of hours searching for Capital Cost Infrastructure Projects I was dismayed to have my thoughts confirmed that Project Cost forecasting is seldom accurate in many cases and the margin of error is astounding to the point that it suggests that the initial cost model that was submitted first for the Go/No Go Decision, and then Contract Placement is at best proven to be a fiction in many cases.  

For example, McKinsey reports that large projects typically overrun budgets by 80%, and Cycle Construction suggested nationwide overruns average 15-25%. These issues are not unique to the UK, with global statistics showing similar trends. 

Further examples of Project Failures include:

  • HS2: The high-speed rail project has faced significant cost increases and delays, making it one of the most expensive megaprojects in the UK.  The initial estimate was £56 billion, which has since ballooned to £106 billion, with potential further increases, according to Full Circle Continuous Improvement,. Factors contributing to this include rising land acquisition costs, complex engineering challenges, and environmental protests.  
  • Aberdeen Western Peripheral Route (AWPR): This Scottish road project experienced a significant cost increase from its initial budget. 
  • London Jubilee Line Extension: This project was significantly over budget and behind schedule. 
  • Scottish Parliament Building: Initially estimated at £10-40 million, the final cost reached £414 million due to a complex and frequently changing design, poor project management, and underestimation of the scope,
  • Channel Tunnel:
    While a vital link, the Channel Tunnel project suffered from significant cost overruns, with the final cost exceeding the initial estimate by 80%. The project also took longer to complete than anticipated. 
  • The Wembley Stadium Reconstruction: The project started with an initial budget of £326.5 million provided by Australian construction company Multiplex. However, the project ended up costing over £1 billion, making it one of the most expensive stadiums ever constructed.

I could continue to list many projects that I fear that the such a list would be exhaustive.

I therefore pose the question, do Project Cost Models provide any value at all when many cost overruns exceed 100%.  Are financial risk models adequate or even understood?  As professionals working in Project Cost and Control, how do we address these issues, and how do we truly measure the effectiveness of what we do as any such metric is only as good as the data and assumptions used?

Parents
  • Nobody involved has any incentive to put in a realistic cost estimate.  When deciding whether or not to go ahead with a big infrastructure project, the politicians will be doing a cost/benefit analysis.  If the benefit is more than the cost, the project goes ahead.

    If the planners submitted a realistic cost estimate, the project would immediately be cancelled.  So instead, they submit a "happy day" estimate where everything goes right first time.  the project gets the go-ahead from the politicians, and everybody involved gets a job for many years to come, managing all the cost overruns.

  • The problem with a 'realistic' estimate is also political in terms of the media fall out from opposition elements. The cost-benefit analysis is more or less the same.

    By the time big projects are commissioned and their lifetime benefits are deprecated, the costs don't matter! (I've heard a similar argument from a senior electrical engineer about nuclear decommissioning cost!)  

  • Hello Simon:

    For government sponsored contracts, terms can be incorporated into the Tier 1 bid requirements (fixed price or cost plus) which can also force them to use  subcontractors (Tiers 2, 3 etc) using the same rules including permanent or temporary employee benefits (wages and retirement funding etc).

    If the UK government changes its contracting requirements the problem could be fixed.

    Peter Brooks

    Palm Bay Florida   

  • Also, wasn't there an article in the E&T magazine a while back about the London Olympic delivery project that did (per article, obviously) deliver on-time. Such are real DEAD-lines.

    Most project milestone just tell you how far you think you've come, and only give a glimpse of how far you've still to go ;-)

  • If the UK government changes its contracting requirements the problem could be fixed.

    Agreed.  I recently heard of a project that had sub-contracted out the work 6 layers deep.  Thus a sub-contractor of a sub-contractor of a sub-contractor of a sub-contractor of a sub-contractor of a sub-contractor.

    They also really need to re-introduce back into the system the CoW (Clerk Of Works)

  • Also, wasn't there an article in the E&T magazine a while back about the London Olympic delivery project that did (per article, obviously) deliver on-time. Such are real DEAD-lines.

    Yes, I know someone well who was very heavily involved in that project. As he puts it: it had to deliver on time as the athletes were arriving then whether it was built or not! However there were (as I understand it) aspects that were scaled back, and don't think about the costs - as my relative put it, towards the delivery date costs became irrelevant, it just had to be completed. It was still a fantastic achievement though. As in a different way was Crossrail / Elizabeth Line, which was the other way around - it was a few years late (compared to the political target, in my experience the project managers knew perfectly well when it would actually be delivered) but it delivered what it intended to deliver. 

    It's always risky to trumpet any project as a "success" or to condemn another as a "failure", in reality they all have lessons we could learn from - both positive and negative.

Reply
  • Also, wasn't there an article in the E&T magazine a while back about the London Olympic delivery project that did (per article, obviously) deliver on-time. Such are real DEAD-lines.

    Yes, I know someone well who was very heavily involved in that project. As he puts it: it had to deliver on time as the athletes were arriving then whether it was built or not! However there were (as I understand it) aspects that were scaled back, and don't think about the costs - as my relative put it, towards the delivery date costs became irrelevant, it just had to be completed. It was still a fantastic achievement though. As in a different way was Crossrail / Elizabeth Line, which was the other way around - it was a few years late (compared to the political target, in my experience the project managers knew perfectly well when it would actually be delivered) but it delivered what it intended to deliver. 

    It's always risky to trumpet any project as a "success" or to condemn another as a "failure", in reality they all have lessons we could learn from - both positive and negative.

Children