So I am looking at a job to install a cable inside a commercial building from an existing 100A 3ph service head to a 9 way TP Ryefield; circa 20M
The client has aggreed with the DNO that it will be a BNO installation, there will be no meters until after the Ryefield fuses.
Choices would seem to be,
External trench around the building or run internally (client prefered)
Stright Con
Split Con
SWA
Singles in trunking (nightmare)
Thoughts?
I wont be deciding, it’s not going on my tickets!
Thanks
Martyn