Cable thoughts?

Hi All, 


So I am looking at a job to install a cable inside a commercial building from an existing 100A 3ph service head to a 9 way TP Ryefield; circa 20M


The client has aggreed with the DNO that it will be a BNO installation, there will be no meters until after the Ryefield fuses.


Choices would seem to be,


External trench around the building or run internally (client prefered)


Stright Con

Split Con

SWA

Singles in trunking (nightmare)


Thoughts? 


I wont be deciding, it’s not going on my tickets! 


Thanks


Martyn


Jesus this new forum malarkey is crap on mobile, it seems to break all the text integration rules.

Parents
  • I used split con to move my consumer unit to the back of my hose. Much easier getting it through joists than 25mm x 3 SWA!

    25mm centre core (live) 25mm eq neutrals and a bare 16mm eq cpc all in one easily handled package. I couldn't ask for more!
Reply
  • I used split con to move my consumer unit to the back of my hose. Much easier getting it through joists than 25mm x 3 SWA!

    25mm centre core (live) 25mm eq neutrals and a bare 16mm eq cpc all in one easily handled package. I couldn't ask for more!