As most of you know I’ve only been qualified for just over a year and I’ve got a quote to do for a cu upgrade.


I know I’m nowhere experienced enough to do EICR’s yet, but what would you guys recommend I check/test before doing the cu upgrade and should I do these checks/tests at the quote stage?
Parents

  • ebee:

    Well Zoom I have seen a few times a ring with no sockets then each socket is on a spur via a JB from that ring.

    Not the most elegant of solutions and breaks with recommended practice of no more points on spurs than points on ring, but no worse than any spur on a ring on a 30/32A OPD all told.




    Hello ebee,

                          I would rather initially connect up new sockets at floor level than struggle about in the loft in the dark with junction boxes spurring off the ring for sockets below. Still them be strange ways in the cuntrysoide boy.


    Z.

Reply

  • ebee:

    Well Zoom I have seen a few times a ring with no sockets then each socket is on a spur via a JB from that ring.

    Not the most elegant of solutions and breaks with recommended practice of no more points on spurs than points on ring, but no worse than any spur on a ring on a 30/32A OPD all told.




    Hello ebee,

                          I would rather initially connect up new sockets at floor level than struggle about in the loft in the dark with junction boxes spurring off the ring for sockets below. Still them be strange ways in the cuntrysoide boy.


    Z.