As most of you know I’ve only been qualified for just over a year and I’ve got a quote to do for a cu upgrade.


I know I’m nowhere experienced enough to do EICR’s yet, but what would you guys recommend I check/test before doing the cu upgrade and should I do these checks/tests at the quote stage?
Parents

  • Fitzy71:

    Then I forgot to put it back on when I was doing my rfc continuity tests to the circuits on the right of main switch and little finger brushed the live tail. 




    That's why you should do dead tests before live tests!

Reply

  • Fitzy71:

    Then I forgot to put it back on when I was doing my rfc continuity tests to the circuits on the right of main switch and little finger brushed the live tail. 




    That's why you should do dead tests before live tests!