Period inspection interval

I am just modifying my condition report templates. I am going to include the the requirements of 653.4 which requires an explanation to support the period determined to the next inspection. That requirement doesn’t seem to have been included in the model form in Appendix 6. Is it included in the NICEIC, NAPIT etc forms?

seems to me that is entirely reasonable to require an explanation as it would, at least for work premises, have cost as well as legal implications.
Parents
  • At what stage does inspection trump testing? So you have an installation with rusty backboxes, no grommets or fly-leads, short tails, loads of spurs off a small ring; but R1+R2, polarity, and Zs are satisfactory. Do you give a short-term pass or recommend a re-wire?
Reply
  • At what stage does inspection trump testing? So you have an installation with rusty backboxes, no grommets or fly-leads, short tails, loads of spurs off a small ring; but R1+R2, polarity, and Zs are satisfactory. Do you give a short-term pass or recommend a re-wire?