I am just modifying my condition report templates. I am going to include the the requirements of 653.4 which requires an explanation to support the period determined to the next inspection. That requirement doesn’t seem to have been included in the model form in Appendix 6. Is it included in the NICEIC, NAPIT etc forms?

seems to me that is entirely reasonable to require an explanation as it would, at least for work premises, have cost as well as legal implications.
Parents

  • Sparkingchip:

    Inspection should always trump testing. 




    I am wary of using terms such as "always" and "never", but I think that's correct; which is why I am spending a day a week re-wiring daughter's house even though all tests were satisfactory.


    Of course, had I submitted an unsatisfactory EICR to a paying customer, it would have been a very different matter.


    So much for the notion of the cobbler's children's shoes! ?


    ETA: at the end of all this, whilst there will now be enough sockets in the office, and lighting will have been improved, the users will notice no difference.

Reply

  • Sparkingchip:

    Inspection should always trump testing. 




    I am wary of using terms such as "always" and "never", but I think that's correct; which is why I am spending a day a week re-wiring daughter's house even though all tests were satisfactory.


    Of course, had I submitted an unsatisfactory EICR to a paying customer, it would have been a very different matter.


    So much for the notion of the cobbler's children's shoes! ?


    ETA: at the end of all this, whilst there will now be enough sockets in the office, and lighting will have been improved, the users will notice no difference.