This discussion is locked.
You cannot post a reply to this discussion. If you have a question start a new discussion

Diversity

Good morning all.


I have a question regarding diversity calc.

So, for example, I have a office unit that has three floors.

There is a main DB feeding the block, each floor has a submain DB feeding three single dbs.

For ease I will make all the DBs the same.

So, the single dbs supply:

3 x 16A Power circuits,

2 x 32A Shower circuits feeding a 7KW shower on each,

1 x 16A Water Heater feeding a 3 KW heater,

1 x 6A Lighting circuit feeding 6 x 20W lights.


So, for diversity I have

Power - (100% x 16) + (50% x (16 + 16) = 32A

Water Heaters - (100% x 30.4) + (100% x 30.4) + (25% x 13.04) = 64.06

Lighting - (90% x 0.52) = 0.46 

Which give a total diverse loading of 96.52 A (100A supply).


Which gives a 300A supply to each submit DB and a 900A supply to the main DB


Is this correct?

Now,  line 9 of table A2 gives a diversity of final circuits.

How would, if I should, apply this.


Thank you in advance.


Richard.

Parents
  • Former Community Member
    0 Former Community Member
    Is the whole building supplied as single phase ?


    As a sensible starting point, what's the gross internal area (GIA) - from there apply something like 35W/m2 to give you a total kW demand (everything credible in an office building)


    If you then take a floor by floor approach and apply a diversity of something like 0.8 to the total figure above and pro rata that back to the total GIA you should then get a sensible value per floor


    From there you should be able to apply at least a factor of 0.8 to the sum total of each floor

    In summary, apply 35w/m2 to the GIA and diversify that by 0.8 per floor and a further 0.8 to collect each floor at the intake (or as a single step, GIA(m2) x 35 x 0.64 = facility W/m2


    You can deduce amps from kW when you have the numbers (remembering if it is 3 phase, you would ideally like some balance across the phases, so assume 33% of demand is on each phase)


    The above is conservative, and includes pretty well everything required like lifts, electrical input into ventilation and other mechanical plant, but doesn't include any electrically driven heating or cooling (VRF, Chillers and the like)


    If you can find a copy, look at the British Council for Offices guidance which might suggest that you actually only need about 15m2 for the office space (power and lighting) - but that's diversified for a reasonably big building where you expect some people to be off site, on leave, in meetings etc)


    Regards


    OMS
Reply
  • Former Community Member
    0 Former Community Member
    Is the whole building supplied as single phase ?


    As a sensible starting point, what's the gross internal area (GIA) - from there apply something like 35W/m2 to give you a total kW demand (everything credible in an office building)


    If you then take a floor by floor approach and apply a diversity of something like 0.8 to the total figure above and pro rata that back to the total GIA you should then get a sensible value per floor


    From there you should be able to apply at least a factor of 0.8 to the sum total of each floor

    In summary, apply 35w/m2 to the GIA and diversify that by 0.8 per floor and a further 0.8 to collect each floor at the intake (or as a single step, GIA(m2) x 35 x 0.64 = facility W/m2


    You can deduce amps from kW when you have the numbers (remembering if it is 3 phase, you would ideally like some balance across the phases, so assume 33% of demand is on each phase)


    The above is conservative, and includes pretty well everything required like lifts, electrical input into ventilation and other mechanical plant, but doesn't include any electrically driven heating or cooling (VRF, Chillers and the like)


    If you can find a copy, look at the British Council for Offices guidance which might suggest that you actually only need about 15m2 for the office space (power and lighting) - but that's diversified for a reasonably big building where you expect some people to be off site, on leave, in meetings etc)


    Regards


    OMS
Children
No Data