On the subject of pulling the DNO fuse.

There have been a couple of reports here of the DNO confronting electricians who have pulled their fuse.


It's getting closer to home, a work colleague was doing a CU change on a domestic house last week, no isolator fitted, so he pulled the fuse (no seals present).

South Nottinghamshire.


Around 90 minutes later there was a knock on the door, a guy from Western Power was investigating a power loss at the property, reported by the Smart Meter phoning home.

He gave the sparky a talking to, and warned they are getting strict in pursuing people who do it, he said meter fiddling was rife, so any loss of power is checked out asap.
Parents
  • Alan, yes, in an ideal world that is true, but I have found since privatization the DNO's have become less responsive than the former electricity boards. A customer wants the work done now, they don't want to negotiate the quagmire of regulatory frameworks etc. We encourage the customer whenever major work is done, to have the DNO install an isolator.  But there are occasions where that's not practical or proportionate.


    However, taking off my 'i want to get on with my job' hat... i fully approve of the procedures around sealing the DNO and metering company's gear... for safety as well as fraud prevention. It's just a shame the average sparky is thrown in with the 'getting free lecky' crowd, and there's not an intermediate procedure available? (temporary seals for registered CPS members for a nominal 5 pounds each would be an idea? with a responsibity to notify the DNO to have the next crew nearby to reseal it properly...). But these days everything is so complex with risk assessments and form filling


    just my £0.02
Reply
  • Alan, yes, in an ideal world that is true, but I have found since privatization the DNO's have become less responsive than the former electricity boards. A customer wants the work done now, they don't want to negotiate the quagmire of regulatory frameworks etc. We encourage the customer whenever major work is done, to have the DNO install an isolator.  But there are occasions where that's not practical or proportionate.


    However, taking off my 'i want to get on with my job' hat... i fully approve of the procedures around sealing the DNO and metering company's gear... for safety as well as fraud prevention. It's just a shame the average sparky is thrown in with the 'getting free lecky' crowd, and there's not an intermediate procedure available? (temporary seals for registered CPS members for a nominal 5 pounds each would be an idea? with a responsibity to notify the DNO to have the next crew nearby to reseal it properly...). But these days everything is so complex with risk assessments and form filling


    just my £0.02