This discussion has been locked.
You can no longer post new replies to this discussion. If you have a question you can start a new discussion

Overhead Catenary Cables to Charge Electric Lorries.

So, what do readers think of this idea?  Surely those large pantographs cause high wind resistance? Perhaps if the lorries were put on steel rails they would be self steering and free up the roads.


From the Beeb. 

https://www.bbc.co.uk/news/av/stories-50223895/could-electric-roads-spark-a-green-transport-revolution


.
  • Sounds horrendously expensive to me.  Trolleybuses worked because buses only followed limited routes.  Trolley trucks would still need big batteries for when they are on minor roads.  It would be cheaper to install fast charging stations at every truck stop.
  • well on heavily used routes to  charge on board batteries provide and traction current without having to stop, maybe. But there is far more height variation in lorries than there is in trains, and on a busy road, you'd need a lot more power stations per km than you do on a railway. 

    A loaded train may be half a dozen megawatts, and on average there will be a few km  between them, while on the M25 for example , each truck would be no more than  100m from the next, probably quite a bit less, and motor size of perhaps 10kW per tonne of GMW. So even for small lorries like 7.5 tonnes, we might think of 70-80kW, and upto half a megawatt for the 44 tonne artics - and that assumes just traction, not charging up the on board batteries at the same time. Even if we dare re-use the train voltage of 25kV RMS, we would have  a lot of amps to think of.
  • It's quite a problem to work with 2 overhead wires. Some experiments were made with direct 3 phase traction in the early days of railways using two wires. The gap between the wires must be greater than the width of the pantograph which restricts the width of the pick up head and hence the allowable amount of sideways deviation. The trolley bus type solution is only suitable for relatively low speeds.

    Would it be better to use multimodal containers so you can gain the benefit of low friction steel wheels on steel rails for the long haul part and use electric trucks for the last 5-10km?


    Best regards


    Roger

  • Roger Bryant:

    Would it be better to use multimodal containers so you can gain the benefit of low friction steel wheels on steel rails 




    We already have steel rails on a number of routes - they are called railways. Electric trucks for the last 5-10km sounds good, until you come to locations where the nearest rails (going by railway station location) are significantly further. However such locations tend to be well away from traffic problems (congestion and pollution) and so there will not be the same pressure for the upgrade.

    Alasdair.

  • I'm inclined to agree, so before messing with roads, perhaps finishing to electrify the railway would be a better start, we only started with the first electric trains in the late 1800s, how hard can it be to just get BrXXX no , no, no, , railway electrification, sorted.   (I think the oldest electric train still running in the UK is the narrow gauge on Brighton seafront dating from 1883)

    Seriously the best energy wise would be a joined up system with more rail freight for long haul, except for the last few miles, which can be smaller lorries that could then be electric. It is not clear why railway lines are empty most of the time, and therefore expensive compared to road transport.

    The only reason a coach is cheaper than a train, ignoring the suggestions in the 1998 song by Divine Comedy, is that the road is very busy, and in effect more people are paying for it. The rail user it seems, is paying for the whole train.
  • As you said on one of the climate threads sometimes you have to change the structure not just try to do a 'Green' like for like.
  • Thinking further about this with reference to Mike's Solar PV and tingles from the flashing post.

    How would you deal with leakage/unbalance currents to avoid the vehicle metalwork rising above normal earth potential especially if one pantograph lost contact with it's wire? 'Traditional' trolley buses operate at 600-750V DC apparently without problems. Would higher voltages and AC cause bigger problems? Conductive tyres could deal with small leakage currents but what about actual faults in the system? Conventional electric rail systems always have a good ground reference.


    Best regards


    Roger

  • How would you deal with leakage/unbalance currents to avoid the vehicle metalwork rising above normal earth potential especially if one pantograph lost contact with it's wire? 'Traditional' trolley buses operate at 600-750V DC apparently without problems. Would higher voltages and AC cause bigger problems?





    The gap between the wires must be greater than the width of the pantograph which restricts the width of the pick up head and hence the allowable amount of sideways deviation. The trolley bus type solution is only suitable for relatively low speeds.



    I did a bit of a 'thought experiment' along these lines a while ago - it was actually thinking about the possibility of re-introducing electric trolley buses but given the increase in congestion on modern roads looking for a way of allowing the bus to connect to the overheads automatically when it was 'in lane' but still being free to move out of lane (and run from small batteries) whenever the need arose. One idea to come out of that was of a 'segmented pantograph' (think something lile the commutator on a universal motor, but perhaps herring-bone shaped to allow smooth transitions of the overhead wire between segments) and two or even three a.c. overhead lines. The lines need only be a few segments apart to prevent shorts (so preventing direct wire-to-wire shorts due to wind movement would more likely be the limit). Each segment would then be connected via a pair of rectifiers (big diodes) - like the first half of a bridge rectifier - to provide unsmoothed d.c. to the vehicle. An automated system would then look to lower the pantograph smartly whenever it was drifting out of lane, and re-connect automatically when the bus was steady under the wires again. By providing a 3-phase supply (or balanced single phase) and by disconnecting the vehicle from the pantograph contacts when anything other than all phases were present, leakage or capacitive coupling currents should mostly cancel out.


      - Andy.
  • And do not make the vehicle class 1 !


    Taking the  commutating pantograph and DC bus idea further, and making those pairs of diodes totem poles of high power FETs, you can then also push power back into the line or take it out, as suits for example during braking.


    Now we have a HVDC reserve, either side of which is at our overhead line voltage depending on instantaneous phase of each cycle.


    We could play a trick, and supply power to the overhead lines in a similar way - i.e. excite each one with an AC plus a DC such that the most negative part of the cycle is near ground - then the negative side of our DC bus, will always be at or near that potential.


    So if we wanted  to use railway like voltages, do 25KV FETs that can switch hundreds of amps exist? - well not as discrete components, yet, the upper bound is a few KV, and you need a factor of 2 or 3 for transients, but techniques do exist for stacking such devices. to make high voltage modules examples

    The next step in any real design then next act is to transform down to a voltage and current more suited to batteries and traction motors, probably the low to mid hundreds of volts . It is the leakage of that transformer from HV to LV through inter-winding capacitance that would need great thought in the choice of switching frequency and core and insulation construction. None of it is impossible with existing parts, but it is certainly in the realms of  bosky powertronics, and not without risks.




  • It is not clear why railway lines are empty most of the time



    I suspect a lot of the problem is the signalling system - mostly still using the Victorian principle of dividing the track into "sections" each of which is guarded by a signal and has to accommodate the stopping distance of the fastest train (and smooth steel wheels on smooth steel track mean they can't exactly stop on a sixpence). So at most one train per section and not in the least flexible if you have a mix of fast and slow traffic. It costs a fortune to adjust anything as it means not only moving the signals, cables and updating the control system but all the track based train detection systems too, not to mention an incredible amount of testing.


    The powers that be would love to run more trains - both passenger and freight - but are up against track capacity issues all over the place. That's why HS2 is so popular with the planners around here - they're not in the least bothered about people getting to London 30 minutes quicker - what they want the fast passenger trains off the existing rails so they can use them for a larger number of slower services - both local passenger and long-distance freight.


       - Andy.