Do we main bond up an installation if a new gas boiler is to be installed when the old one is removed?
I don't understand. What has a new boiler got to do with Main Bonding requirements?
What are extraneous-conductive-parts, and what are not?
See Part 2 in BS7671.
Now, to put a spanner into the works, do any issues arise if the copper pipes are "bonded" with solderless copper bonding?
No.