A TT installation with an ELCB in the tails upfront of a metal consumer unit with a main switch and single pole 30 mA RCBOs for each individual circuit.
How would you code it for an EICR?
Take your time having a proper look at it before announcing your decision.
I went to install a supply for a bathroom towel rail, the builder had taken a plug socket off leaving the wires sticking out of the back box having turned the circuit off at the single pole RCBO.
I looked at it and said to the bathroom fitter are the cables still live? I don't know was his reply so I tested them.
I went to install a supply for a bathroom towel rail, the builder had taken a plug socket off leaving the wires sticking out of the back box having turned the circuit off at the single pole RCBO.
I looked at it and said to the bathroom fitter are the cables still live? I don't know was his reply so I tested them.