As per subject, I was asked this morning about the practicalities for EV provision by an electrician. Apparently, it has been stipulated as a condition of granting planning permission for some new build dwellings, so I asked for sight of this.


Whilst it is usual for the planning to seek comments from the water authority for sewage disposal, I doubt if the DNO has been consulted.


Has anyone else come across this?


Regards


BOD
Parents
  • Former Community Member
    0 Former Community Member
    At some stage, the developer will apply for an electricity supply of a certain size


    I wonder if the DNO's standard 12/15/16 kVA with a diversity after max demand of 2 kVA or so, change to one of 20+ kVA with 10 kVA demand, ie five times the infrastructure cost?


    I wonder if our resident UKPN spokesperson will advise?


    Regards


    BOD
Reply
  • Former Community Member
    0 Former Community Member
    At some stage, the developer will apply for an electricity supply of a certain size


    I wonder if the DNO's standard 12/15/16 kVA with a diversity after max demand of 2 kVA or so, change to one of 20+ kVA with 10 kVA demand, ie five times the infrastructure cost?


    I wonder if our resident UKPN spokesperson will advise?