What would you consider a 'basic/standard' install?

Former Community Member
Former Community Member
Hi all


I'm after some advice to settle a dispute with a client.


I was asked to provide a provisional sum for a standard installation in a single story extension for a living room so I put in about £1800 to cover four double sockets and a central light given that there was no spec from the client and that's what I would class as being a basic/standard install in a new room.


The client has now said that they want a 15 spotlight lighting array and 10 double sockets which is more than what I'd allocated for in the original provisional sum but they're saying that they want it all done for £1800 as I had 'quoted' for.


They are arguing that they consider a 'basic/standard' install to be 15 spotlights and 10 double sockets for a living room??? I've tried to explain that a provisional sum is just an estimate...


I can't walk away as they still owe me for the kitchen install and I get the feeling that they won't pay for that unless I do the extra work for £1800


Am I being unreasonable?

Parents

  • Might be a really, really big extension Chris and a long, long way from the CU!




    1) "  conceal all cables including to chase into and make good in matching stone and grout, and to re-polish the marble pillars as required .."

    Or

    2) " to nail twin and earth cables across wall at 45 degrees and make good by covering over surface cable and associated clips with slightly creased woodchip wallpaper "



    Depends on the job specification ; I suspect it is nearer the former. The  latter would be expensive at 10% of the price, at least here


    A lot of the time, and so the money, is in the finish required. 4 sockets surface mounted with mini-trunking on a bare wall takes minutes, chased in , plastered and painted could be days.


Reply

  • Might be a really, really big extension Chris and a long, long way from the CU!




    1) "  conceal all cables including to chase into and make good in matching stone and grout, and to re-polish the marble pillars as required .."

    Or

    2) " to nail twin and earth cables across wall at 45 degrees and make good by covering over surface cable and associated clips with slightly creased woodchip wallpaper "



    Depends on the job specification ; I suspect it is nearer the former. The  latter would be expensive at 10% of the price, at least here


    A lot of the time, and so the money, is in the finish required. 4 sockets surface mounted with mini-trunking on a bare wall takes minutes, chased in , plastered and painted could be days.