We don’t have part P but can you tell me, just as a matter of interest, what document is issued by a BC appointed contractor following the inspection of work carried out by someone not registered?
Depends upon how involved the BC contractor has been from the start of the job.
If the job was notified from the outset and regular monitoring has taken place throughout, then I think it would be in order for a EIC to be issued.
If not, and work has been covered up before being notified, then the contractor can only issue a periodic inspection report with the appropriate limitations highlighted and applied.
It is down to the judgement of the contractor in the end.
Depends upon how involved the BC contractor has been from the start of the job.
If the job was notified from the outset and regular monitoring has taken place throughout, then I think it would be in order for a EIC to be issued.
If not, and work has been covered up before being notified, then the contractor can only issue a periodic inspection report with the appropriate limitations highlighted and applied.
It is down to the judgement of the contractor in the end.