We don’t have part P but can you tell me, just as a matter of interest, what document is issued by a BC appointed contractor following the inspection of work carried out by someone not registered?
When I last did this, I was initially issued with an Electrical Installation Condition Report. This recorded a couple of unsatisfactory elements. These were retested once rectification was complete, a Minor Electrical Installation Works Certificate issued. These were all provided to me via Building Control. Once other elements of the build were complete I was issued with a completion certificate from Building Control. I have just applied under a Building Notice to undertake further works and am expecting the same reports (without the unsatisfactory elements). Funnily enough my BC Inspector called this morning to confirm we will be going through the same process (and to confirm the fee).
When I last did this, I was initially issued with an Electrical Installation Condition Report. This recorded a couple of unsatisfactory elements. These were retested once rectification was complete, a Minor Electrical Installation Works Certificate issued. These were all provided to me via Building Control. Once other elements of the build were complete I was issued with a completion certificate from Building Control. I have just applied under a Building Notice to undertake further works and am expecting the same reports (without the unsatisfactory elements). Funnily enough my BC Inspector called this morning to confirm we will be going through the same process (and to confirm the fee).