gkenyon:
That's very interesting ... how is the TT installation immediately adjacent to the PME supplied installation separated from the PME earthing system?
For us, the issue would be two or more PME services into different areas of a steel building. It would be possible for the steelwork of the building to carry diverted neutral currents, for which it almost certainly would not be rated.
Regards,
Alan.
gkenyon:
That's very interesting ... how is the TT installation immediately adjacent to the PME supplied installation separated from the PME earthing system?
For us, the issue would be two or more PME services into different areas of a steel building. It would be possible for the steelwork of the building to carry diverted neutral currents, for which it almost certainly would not be rated.
Regards,
Alan.