Hi I have been asked to help with a temporary supply to a takeaway shop that has no electric meter. 


I am thinking of Hiring a 10KVa generator to provide the supply but have never dealt with a job like this before.


Would love some opinions and guidance right now, would be much appreciated.


Also would this be classed as notifiable works?


Many thanks 


Amardeep Singh
Parents
  • Former Community Member
    0 Former Community Member
    Thanks for all your input guys.


    I walked away from the job. Advised the chap to hold tight until the supplier reinstates the supply.


    I told him its too messy and too many people involved. There was the client, franchise owner, landlord, neighbour and supplier. 


    A lot of people to liase with and make sure everyone is happy.
Reply
  • Former Community Member
    0 Former Community Member
    Thanks for all your input guys.


    I walked away from the job. Advised the chap to hold tight until the supplier reinstates the supply.


    I told him its too messy and too many people involved. There was the client, franchise owner, landlord, neighbour and supplier. 


    A lot of people to liase with and make sure everyone is happy.
Children
No Data