Hi I have been asked to help with a temporary supply to a takeaway shop that has no electric meter. 


I am thinking of Hiring a 10KVa generator to provide the supply but have never dealt with a job like this before.


Would love some opinions and guidance right now, would be much appreciated.


Also would this be classed as notifiable works?


Many thanks 


Amardeep Singh
Parents
  • I know of one that was about £40 over and the meter was fed (Ticket like cards) to get power on in a similar situation although emergency credit was £5 before cut off. I asasumed it was a mixture of standing charges and perhaps previous agreed arrears scheduling but £700 WOW
Reply
  • I know of one that was about £40 over and the meter was fed (Ticket like cards) to get power on in a similar situation although emergency credit was £5 before cut off. I asasumed it was a mixture of standing charges and perhaps previous agreed arrears scheduling but £700 WOW