lyledunn:
You can use the PME terminal with one condition being
PME earthing facility shall not be used as the means of earthing for an installation falling within the scope of this section except where:
(i) the installation is continuously under the supervision of a skilled or instructed person(s), competent in such work, and...
I have visions of a Spark dressed as a palace guard marching up and down outside the container! Can someone expand on this exception?
It's historical and related to BBC outside broadcast units I understand.
Take a look at the proposed change to that Regulation in the Amendment 2 DPC.
lyledunn:
You can use the PME terminal with one condition being
PME earthing facility shall not be used as the means of earthing for an installation falling within the scope of this section except where:
(i) the installation is continuously under the supervision of a skilled or instructed person(s), competent in such work, and...
I have visions of a Spark dressed as a palace guard marching up and down outside the container! Can someone expand on this exception?
It's historical and related to BBC outside broadcast units I understand.
Take a look at the proposed change to that Regulation in the Amendment 2 DPC.