Gus Carrie:
Yes EICR as the client didn’t get a certificate for their extension when it was built.
...
The 250V IR test was done across line and neutral which have almost a perfect short due to USB charging sockets.
So was this a typo?
Cores removed from the terminals. Including earth cores removed from the MET.
@500V
Between line and neutral >999 MΩ
Between neutral and earth >999 MΩ