411.4 TN system
411.4.1 In a TN system, the integrity of the earthing of the installation depends on the reliable and effective
connection of the PEN or PE conductors to Earth. Where the earthing is provided from a public or other supply
system, compliance with the necessary conditions external to the installation is the responsibility of the distributor.
411.4.1 In a TN system, the integrity of the earthing of the installation depends on the reliable and effective
connection of the PEN or PE conductors to Earth. Where the earthing is provided from a public or other supply
system, compliance with the necessary conditions external to the installation is the responsibility of the distributor.
I don't get why a section about SPDs in a TT system refers to a TN requirement.