Conduit requirements and cable type

Former Community Member
Former Community Member

I’m in the process of installing seven hard wired fire alarms into our property all of which have to be interlinked.



I intend to re use a now empty steel conduit that runs from right beside our consumer unit up into the loft space. The steel conduit at its point of entry into the loft terminates there presumably the rest was removed in the past. I want to run a cable from there which will have to do an up and over brickwork in the loft.



My first question, is it acceptable in compliance with electrical regulations to simply clip the cable to the brick at the mortar joints or do I have to or even if strictly not necessary should I, put the cable in PVC conduit? This area is not trafficked.



Once I have crossed the brick work and come down to the first alarm, from there I intend to run a cable down the near center of the loft adjacent to the walkway in pvc conduit parallel to the 2 existing lighting circuit conduits located above the joists. I am not going to drill through the joists. At points along the conduit there will be junctions to allow clipped cable not in conduit to be ran parallel to the joists to the relevant alarm. The conduit is going to be a straight run, so my question is having consulted a few sources that state 1.5mm flexible cable not twin and earth must be used in conduit, does it? I understand the reason for flexible cable in conduit with a lot of turns and junctions but this is a straight run.


Thanks


Parents
  • Which simultaneously touchable objects are you bonding here - flat gas pipes and flat wiring, of whole building gas pipes, and whole building MET. ?

    Main bonding should be building incomers (gas and electric) Flat bonding needs to be local to the flat.


    A 22mm pipe has more copper cross-section than a 10mm cable, so if it runs the right way, get it nearer  the ends,

    Regs do not prohibit earthing sharing a duct, but  the laws of physics might - I think it will be hard to thread unless it is a very easy route.

    mike.
Reply
  • Which simultaneously touchable objects are you bonding here - flat gas pipes and flat wiring, of whole building gas pipes, and whole building MET. ?

    Main bonding should be building incomers (gas and electric) Flat bonding needs to be local to the flat.


    A 22mm pipe has more copper cross-section than a 10mm cable, so if it runs the right way, get it nearer  the ends,

    Regs do not prohibit earthing sharing a duct, but  the laws of physics might - I think it will be hard to thread unless it is a very easy route.

    mike.