Looping 16mm through a main switch

I need to split a 16mm t+e to feed a second CU.  Loading is not an issue.  Does anyone see a problem with me looping them through the 100 amp main switch.  2 16mm cores sit very nicely side by side and makes things a whole lot simpler and tidier.  The CU instructions say that the main switch will take up to 50mm.



Gary
Parents
  • Wylex "Extenso" Zoom lad?.

    Yes the cage clamps of today are poor compared with the old double screws tunnel terminals of yesterday and I`d be thinking tail block in first instance
Reply
  • Wylex "Extenso" Zoom lad?.

    Yes the cage clamps of today are poor compared with the old double screws tunnel terminals of yesterday and I`d be thinking tail block in first instance
Children
No Data