Good day to all
… in these scenarios:
From new service head position to existing consumer unit no change in length/csa ?
From new service head position to existing ‘henley’ block (serving multiple CUs); no change in length/csa ?
As previous with change in length (still ≤ 3m) and conditions (but no real affects to CCC or Ze PFC) ?
As previous but adding Switch Fuse Isolator unit (just for kicks) and still ≤3m ?
Or meter tails alterations are always an EIC regardless (as I would consider) ?
I did come across a post or two suggesting MEIWC as existing circuit alteration, but the impact could be greater.
By the way [not], what that is relevant would one fill out on a model EIC Sched. of Test Results (or MEIWC if one was so inclined) for a ‘meter tails’ alteration ?
Regards,Habs