This discussion has been locked.
You can no longer post new replies to this discussion. If you have a question you can start a new discussion

Inspection & Testing

I am a project manager, constructing new waste water treatment works, for a water company. The contractor building the new works has provided a program which has 4 months between  part 1 (dead testing) and part 2 (live testing) of the NICIEC certification. In between these dates, the contractor will test and commission of the plant and equipment e.g. pumps, actuated valves, instrumentation, screens etc.

Would it be correct to say, this does not comply with the wiring regulations ? 

Parents
  • The contractor has complete responsibility for the program. Before construction begins the contractors program must be agreed with the project manager. The program cannot change thereafter without the pm's approval.

Reply
  • The contractor has complete responsibility for the program. Before construction begins the contractors program must be agreed with the project manager. The program cannot change thereafter without the pm's approval.

Children
No Data