IDNO/ICP

Former Community Member
Former Community Member

Hello Chaps/Chapesses, 

I've been asked to look at using an IDNO/ICP to undertake the contestable part of a new connection, the client is hoping it will save some money rather than the DNO doing all the works. The list of providers is slightly overwhelming so I thought I would see if anyone has done this before and had any recommendations? 

It's a new 500kVA substation and 7 individual 3 phase connections to industrial units. 

Thanks in advance! 

Parents
  • Former Community Member
    0 Former Community Member

    This is from WPD so it looks like your scenario is in the 14 week timescale Amanda.

    Dare I ask when the site got planning permission and when the client realised he might actually need an electric supply?!!!!

    Regards

    BOD

     

    Struggling to get a link so apologies for untidy post but it is hidden in new connections/price guide/on demand.

    Got it to cut & paste!!!!
     

    Connection TypeGuaranteed StandardAverage time to receive a quotationPrices from (excl.VAT)Average prices (excl.VAT)Average time to get a connection from payment
    1 standard domestic connection5 days4 days£450£2,0004 Weeks
    Up to 4 standard domestic connections
     
    15 days5 days£1,800£5,0005 Weeks
    Over 4 domestic connections (based on typical 5 connections with service works only)
     
    25 days7 days£1,890£15,0006 Weeks
    Typical small business connection
    (up to 69kVA)
     
    15 days5 days£452£4,0005 Weeks
    Multiple small business connections (based on typical 2 connections with low voltage service works only)
     
    25 days8 days£3,812£12,0006 Weeks
    Typical large business connection (HV)
     
    35 days8 days£14,212£65,00014 Weeks
    Extra high voltage connection
     
    65 days50 daysPrice on requestPrice on request2 Years
    Unmetered new connections (excluding Local Authority & PFI)
     
    25 days7 days£298£2,4175 Weeks

     

     

    • Demand new connections

    Notes

    - Average time to quote is counted from the date the application form has been received from the customer.

    - Average time to connect is counted from the date the payment for connection is received from the customer.

    - These timescales are an indication only and may not reflect final timescales included in any regulatory returns following a data assurance process.

    - ‘Prices from’ are provided on the basis of an existing network being available within 10m of each connection location. These indicative charges exclude any excavation/reinstatement, reinforcement, extension assets, diversion works or legal consents and land rights.

    - These costs are for general illustration purposes only and are not to be relied upon should you require a more accurate price in respect of specific premises.

     

Reply
  • Former Community Member
    0 Former Community Member

    This is from WPD so it looks like your scenario is in the 14 week timescale Amanda.

    Dare I ask when the site got planning permission and when the client realised he might actually need an electric supply?!!!!

    Regards

    BOD

     

    Struggling to get a link so apologies for untidy post but it is hidden in new connections/price guide/on demand.

    Got it to cut & paste!!!!
     

    Connection TypeGuaranteed StandardAverage time to receive a quotationPrices from (excl.VAT)Average prices (excl.VAT)Average time to get a connection from payment
    1 standard domestic connection5 days4 days£450£2,0004 Weeks
    Up to 4 standard domestic connections
     
    15 days5 days£1,800£5,0005 Weeks
    Over 4 domestic connections (based on typical 5 connections with service works only)
     
    25 days7 days£1,890£15,0006 Weeks
    Typical small business connection
    (up to 69kVA)
     
    15 days5 days£452£4,0005 Weeks
    Multiple small business connections (based on typical 2 connections with low voltage service works only)
     
    25 days8 days£3,812£12,0006 Weeks
    Typical large business connection (HV)
     
    35 days8 days£14,212£65,00014 Weeks
    Extra high voltage connection
     
    65 days50 daysPrice on requestPrice on request2 Years
    Unmetered new connections (excluding Local Authority & PFI)
     
    25 days7 days£298£2,4175 Weeks

     

     

    • Demand new connections

    Notes

    - Average time to quote is counted from the date the application form has been received from the customer.

    - Average time to connect is counted from the date the payment for connection is received from the customer.

    - These timescales are an indication only and may not reflect final timescales included in any regulatory returns following a data assurance process.

    - ‘Prices from’ are provided on the basis of an existing network being available within 10m of each connection location. These indicative charges exclude any excavation/reinstatement, reinforcement, extension assets, diversion works or legal consents and land rights.

    - These costs are for general illustration purposes only and are not to be relied upon should you require a more accurate price in respect of specific premises.

     