Paperwork after rewire?

I would be grateful if the experts here could tell me what paperwork I should expect having just had a new CU and complete rewire of a house.   At the moment I have a certificate from NICEIC but all it states is “Building Regulations Certificate of Completion”, but nothing else.  Should I expect more?  When I last had this done at a different house I was given a list of works completed with test results, but I do not know what is expected now.

Parents
  • Yes, you should have a completed EIC (Electrical Installation Certificate), with all the test results and check lists of other things. You should report the contractor to the NICEIC and NOT PAY the bill until all is in order.

Reply
  • Yes, you should have a completed EIC (Electrical Installation Certificate), with all the test results and check lists of other things. You should report the contractor to the NICEIC and NOT PAY the bill until all is in order.