Closing this down because the answers are increasingly off topic and missing the point.
Two ways of looking at this:
(1) Do as you are told; or more formally, do what it says in the contract. I am not sure what "simple test" means - is that just pressing the test button?
(2) Test the RCD properly. Yes, a satisfactory response to the test button shows that the RCD still functions to a certain level, but in the absence of paperwork, I think that ideally the trip time (at IΔn) should be tested. I think that testing it somewhere down the circuit is more than intended because then you are testing the circuit as well, so just test the RCD in the DB.
Two ways of looking at this:
(1) Do as you are told; or more formally, do what it says in the contract. I am not sure what "simple test" means - is that just pressing the test button?
(2) Test the RCD properly. Yes, a satisfactory response to the test button shows that the RCD still functions to a certain level, but in the absence of paperwork, I think that ideally the trip time (at IΔn) should be tested. I think that testing it somewhere down the circuit is more than intended because then you are testing the circuit as well, so just test the RCD in the DB.