We have a design in place to replace old switch gear but the design was done during the pandemic and we are not due to install until October 2022.

Is it possible to carry out the install to the 18th Edition A1 or must it comply with 18th Edition A2? .

I know with previous amendments to the BS7671 it was acceptable to install on a design from previous edition but it seems to ring a bell during a tech talk i attended they said this was not the case this time.

My main concern is that the design does not allow for any surge protection but i feel it should be installed.

Any clarification would be appreciated.

Parents
  • A few years ago when then upgraded earthing to 16mm from 10mm I justr happened to be an inspector on the electricity board and I had to go and connect a couple of roads on a new housing estate.

    It just happened that I knew that the contractors had had 2 years notice that after a certain date , supplies would not be connected unless they had 16mm earthing so naturally i failed the lot. Shall I just say that not long afterwards we parted company as I wasn't supposed to know about the 2 year notice period had been given. (mind you few others had!) and I had the letter to prove it!

Reply
  • A few years ago when then upgraded earthing to 16mm from 10mm I justr happened to be an inspector on the electricity board and I had to go and connect a couple of roads on a new housing estate.

    It just happened that I knew that the contractors had had 2 years notice that after a certain date , supplies would not be connected unless they had 16mm earthing so naturally i failed the lot. Shall I just say that not long afterwards we parted company as I wasn't supposed to know about the 2 year notice period had been given. (mind you few others had!) and I had the letter to prove it!

Children
No Data