Overall Diversity in huge commercial kitchen

Good afternoon

If anyone has any knowledge or gut feeling please go on and share it with me

We a well known restaurant/pub that is expected to be busy

There is a good 300A of installed power in the kitchen only

Unfortunately the power supply for the whole installation (including mechanical loads, front of house, bar, back of house etc) is a frugal 315A

So, taking into consideration that kitchen is the heart and sould of the place what do you think should be a realistic diversity to be applied on this 300A of connected load?

My initial thoughts were 50% bringing it down to 150A of constant current

However an older and much more experienced engineer proposed something along the 75% mark.

Does anyone have any similar real life experience with this?

Any insights are highly appreciated

Cheers

Parents
  • What else of the rest of the load can be cut back at peak times - is heating gas or electric, if electric can it be time shifted - once the place is full it may not need so much. What are the 'mechanical' loads? Is their air con/ extraction running - all that 200kW of mostly heat (300A per phase right ?) has to get out of the kitchen somehow .Is there heat recovery ?

    If nothing else the  leccy bill will focus attention on not leaving things running if not needed.

    I suspect it will be OK actually but no-one's estimate will be particularly correct.

    Mike

Reply
  • What else of the rest of the load can be cut back at peak times - is heating gas or electric, if electric can it be time shifted - once the place is full it may not need so much. What are the 'mechanical' loads? Is their air con/ extraction running - all that 200kW of mostly heat (300A per phase right ?) has to get out of the kitchen somehow .Is there heat recovery ?

    If nothing else the  leccy bill will focus attention on not leaving things running if not needed.

    I suspect it will be OK actually but no-one's estimate will be particularly correct.