I'm trying to arrange a SEG tariff for an installation that was done just after the end of the FIT scheme. The property, a church, has a 3 phase meter though the solar panels feed only one phase, the one that carries the most daytime load.
Our current supplier, Total GP do not offer a SEG.
Octopus, an obvious choice, do offer one where they do not have a supply contract but require a smart meter which meters the export.
TotalGP refuse to install a smart meter.
Where do I go with this?