For a new building (large warehouse) what documentation would you expect to receive from the main M&E contractor on the lighting protection system?

Certificates in addition to the electrical installation cert

As fitted drawings

Parents
  • Does BS EN 62305-2 offer any advise as a starting point?

    On completion of the works the whole system shall be commissioned by a competent person and all relevant commissioning data shall be recorded and shall append the commissioning certification. Commissioning certificates will be issued on completion.