EIC or MWC

Scenario:

Existing lighting circuits with fluorescent luminaires upgraded to LED equivalents.

Circuit breaker changing type and/or rating.

Contractor has provided an MWC covering the works.

All looks good, but because the circuit protective device is not strictly a like for like change, should they have actually provided an EIC?

Parents Reply Children
  • Unfortunately not, but it was the same as the BS7671 model form. It was correctly filled in, but the Q was raised, should it have been an EIC?