Morning all,
Looking for some advice - we've applied for a power upgrade to a school (circa 500kVA) and the DNO have given us the option of 2No 400A cut-outs from the same the same transformer. The supplies will be terminated into separate cut-outs and my question is, does everything in front of the meter need to be split across the 2 supplies or can it be considered as a general parallel supply? It feels like a slightly unorthodox way of supplying a single building and feel there's quite a high risk from an isolation point of view, LV interleaving etc.