The new mains cut out and metering are being installed shortly , this will feed a 250A Panel board adjacent to the service head. The panel board will have a four pole 200A MCCB as a main switch and will therefore isolation all of the upstream installation. It seems pointless installing a separate main switch but will the supplier accept this and will it comply. UKPN and the electricity supplier are sitting on the fence , well they would be if you could talk to anyone !