Outside lighting and cable run around a lake

Hi Folks, I am working on a fishery with a house on it that will be air B+B’d. The client wants outside lighting all around the property, front and rear. 3 of the circuits will be running around two lakes. There is a lot of trees, roots and obstacles, so the client does not want to dig trenches to run the cables underground. I am going to use either wise box’s or Shelly Pro 3’s to control all the circuits. The feeds to each control will be trenched, it is just the load runs that cannot be trenched. 
Could anyone help advise me on the running of cables around the lakes. I would like to run the cable in SWA, but as it is a commercial let property I am in a quandary over best practice and regs/ safety. Many thanks. Regards Giles 

Parents
  • if its traditional  lamp posts, then overhead cable between them may be possible.
    SWA is OK above-ground regs wise but in practice is  prone to damage if it can be driven or walked over, and if you are not careful even if when tacked up to concrete posts or a fence it can end up looking like railway track-side wiring, which may not really be the customer's intention...  

    It might be worth considering a mix of exposed on fences or similar and shallow burial under paving slabs or similar 

    As above moles, either the slit-plough kind or the two trenches air  impact hammer kind  can be very good, but you need to know what is already underground there to avoid it, and putting the catch trench for the impact kind in the right place is a bit of a knack. . There are companies that specialise in putting ducting in that way but its not as simple as hiring the kit and assuming that it always works.

    Solar lights might be an option, but not if any real brightness or reliability is required.

    Mike

  • Thanks for the reply Gary and Mike, very helpful. it’s the usual client response. I need it done yesterday so a mole being a brilliant solution but not time practical. I was unsure if SWA would be compliant in this scenario , as, with the regs, they leave it slightly open to your judgment, saying it must be protected from impact ect ect .. I will need to think on this some more and possible quote with SWA direct on floor with visible markings at certain points, it will come up to posted and glanded every 10m or so to go to a spike light too, so it will be visible, I may also, put a risk assessment in and a document that the client signs to show they have been explained all the risks? Again, many thanks for your replies

Reply
  • Thanks for the reply Gary and Mike, very helpful. it’s the usual client response. I need it done yesterday so a mole being a brilliant solution but not time practical. I was unsure if SWA would be compliant in this scenario , as, with the regs, they leave it slightly open to your judgment, saying it must be protected from impact ect ect .. I will need to think on this some more and possible quote with SWA direct on floor with visible markings at certain points, it will come up to posted and glanded every 10m or so to go to a spike light too, so it will be visible, I may also, put a risk assessment in and a document that the client signs to show they have been explained all the risks? Again, many thanks for your replies