Heathrow Closure

Unbelievably I can't see a discussion thread on this already.

Anyone actually believing that a single transformer/substation fire shuts fully down one of the largest airports in the world?  

Mod edit: including a link for context  

Parents
  • I have seen reports of the cost to Heathrow airport for the incident being in the region of £20m - with costs to the wider industry and economy boutne by others.  Given that Heathrow has grown organically with demand being added over decades, i wonder how much of the situation arose because the problem became too big to solve. 

    All supplies to the site were connected to a single feeder - my initial thought was to wonder why the load was not distributed across the avialble feeders, but if it would have taken half a day to reconfigure the supplies, with multiple system shut downs required then perhaps a reconfiguration was deeemed not feasible or not palatable.

    Looking at the cost - If there are wide spread loads (critical and non-critcal) that are not generator backed across the site, then a project to cover these with generators would cost tens of millions - probably in excess of the quoted £20m loss to 'Hetahrow Airport Limited'.  Perhaps there was always an awareness of the risk but a conscious decision not to mitigate 

  • I wasn't suggesting that everything needed to be done in one night. There is such a thing as staging over weeks or months. 

    What happens when the airport has to close because of bad weather (example Fog).

    My wife experienced a situation many years ago when her fight into London was delayed because of bad weather and her plane was diverted into a airport in Scotland for a few hours.

    Just think what happens when the local clocks are changed in spring and fall and the airlines are forced to adjust their schedules.

    Peter Brooks

    Palm Bay FL

  • Not sure what happened at Heathrow but for sure the emergency lights worked and presumably the control tower standby generator but security devises in passport control and computers were probably run off the airports mains power circuits which were not backed up with emergency generation.

    Same with the baggage handling equipment.  Hopefully, Heathrow have by now installed these critical areas with standby plant as it certainly should not cost as much as £20 million.

  • Have a look in this thread for one of my previous post with attachment where I simply put

    Worth a read

  • The cost to the Heathrow reputation is 10 times more than the stated financial cost of £20m.  It is also worth looking at who were the decision makers and who has just sold off a large share of Heathrow airport from their portfolio. 

  • Final report published today https://www.neso.energy/document/363891/download 

  • Thanks Chris.

    An interesting read (with some lessons in the detail) although sadly at the highest level does sound like the common "opportunities were missed" maintenance failure.

  • "Using forensic analysis from both National Grid Electricity Transmission and London Fire
    Brigade, this review has seen evidence that a catastrophic failure on one of SGT3’s high
    voltage bushings caused a fire to ignite on the supergrid transformer. This was most likely
    caused by moisture entering the bushing causing a short circuit. The electricity likely then
    ‘arced’ (causing sparks) which combined with air and heat to ignite the oil, resulting in a fire.
    2.4 An elevated moisture reading in one of SGT3’s bushings had been detected in oil samples
    taken in July 2018. According to National Grid Electricity Transmission’s relevant guidance, such
    readings indicate ‘an imminent fault and that the bushing should be replaced’. While the
    reading was recorded in National Grid Electricity Transmission’s online system, the mitigations
    appropriate to its severity were not actioned."

    So that is the nature of the network fault, but, and it is quite a big but, why, given Heathrow has 3 in-feeds, could they not switch over to the other 2 and keep going - clearly that is what National Grid expected would happen as they did not consider the transformer bushing a priority - and presumably would have had to power some kit off to change it anyway.
    Mike

  • If you mean the airport, with three infeeds, I'd say by the read of it they could (and did within 6-7 hours from memory) but it required manual intervention. Probably this was in part due to SSEN enforcing open points to ensure that their feeders aren't paralleled through the customer's network (usually this means transferrable key interlocks etc).

    If you mean the Hyde 66kV SS, the first SGT tripped and the substation did indeed recover using the third SGT which was provided as a running reserve. But the fire caused the second SGT to trip a little bit later either due to fire damage to its control kiosk or exploding bushings, and the third SGT was taken out automatically by the control scheme as it wasn't designed to operate solo.

  • Still does not explain why Heathrow internal network relied on manual switching to re-configure their network.Most

    large hospitals have  automatic reconfiguration of their own network in event of a fault.

    And sufficient on site generation to run the whole hospital.

    Surely Heathrow should have the same on their site??

  • There's also a LinkedIn comment at https://www.linkedin.com/posts/simoncgallagher_heathrow-neso-powercut-activity-7346083051480707073-KKrU (I've stripped the tracking codes) highlighting that Heathrow should also be taking much of the blame.

    [It was their battle to lose, as much by their inability to utilise the multiplicity of supply points]

Reply Children
  • You can see if from both sides.

    The network companies knowing the intricacies of their network design, point to Heathrow having supplies from several different substations, placing the responsibility on Heathrow as a very large and well resourced customer to be able to operate from any of the incoming supplies.

    Heathrow's affected substation A had two separate incoming supplies from the DNO and it is the end customer, it cannot be assumed to know the intricacies of the network company's network configuration which are beyond its control. Heathrow may have assumed that two separate supplies to substation A was sufficient redundancy, that those two incoming supplies should have sufficient independence such that they should not both fail at once. Further, the restrictions on parallel interconnection between different substations imposed by the network companies meant the use of any within-site interconnectors would be highly restricted anyway.

    The topic of independence is key to the whole incident, people focus on the bushing failure which was the trigger, but it was the lack of a functioning fire deluge system (due to the failure to repair the long standing fault on the fire pumps) which allowed the incident to escalate. The deluge system was there to prevent a fire on one transformer (SGT3), compromising the independence of the adjacent transformer (SGT1) and even after the initial failure of the bushing on SGT3, SGT1 continued to function for 20 minutes as the fire raged on SGT3. SGT1 finally tripping off as the fire incinerated its marshalling kiosk. At which point, SGT2 which was physically independent of SGT1 and SGT3, at the other side of the sub, but electrically dependent on SGT1 sharing the same feed also tripped off which resulted in the loss of supply.

    Looking at the incident as an outsider, clearly the bushing failure was the cause of the SGT3 failure, but it was the lack of the functioning fire deluge system combined with the lack of independent 275kV supplies to SGT2 which escalated the incident to cause the loss of supply.