That initially sounds like a good suggestion, and if both TT, might have addressed the 411.3.1.1 requirement. BUT, there are a couple of other considerations. For example, if they are not connected to the same supply transformer, or any of the TT earth electrodes are too close to PME buried earth (or worse, HV!) then you might have an issue with impulses and fault transfer potential.
Which is why there is another fundamental requirement of BS 7671 - 542.1.3.3, which says you need to be very, very careful bonding earths of different installations together, and you take full responsibility for that.
I appreciate that increasing numbers of EV points, or even non-electrified street furniture, mean that the available spaces are disappearing, but what has been done to date? How have you coped so far?
It's incredibly difficult and we are trying to find an electrical solution which reduces or negates the need to be a certain distance from other installations or street furniture, we also have to comply with many other factors as well, such as noise pollution to the adjacent properties, light intrusion if there are windows next to where we want to put them, if there's any underground structures we can't dig through... the list goes on! There's actually a pretty good document which outlines the requirements of EV charging points - http://ukevse.org.uk/resources/procurement-guidance/
Are you responsible for the design or the install only?
I can see the earthing of EVC points being a major headache in a cramped city centre with existing street lighting, CCTV, ANPR, comms cabinets and so on.
I've never been involved in EVC. I was talking to an estates manager this morning that has been instructed to arrange for 500kW of EVC to be installed at their site.
Time for some CPD.
Regards
Parsley
I essentially am part of the install only as the client provides their own charge points which are all pre-built and shipped over, but I'm sure if we can come to an agreement or a redesign then this could change. We install mainly 7kW and 22kW charge points.
500kW of EVC's Is one hell of a lot. I know Tesla have unveiled a 250kW charge point which requires a 1MW transformer to power 4 of them but we simply don't have the infrastructure to cope with that at the moment. I was asked to look at an install elsewhere as someone wanted to know how many 50kW rapid chargers would fit in the car park - long story short, they didn't go with it as it required a new HV supply to a brand new substation for a few charge points which would have been too powerful for the nature of the car park. (you wouldn't really have a 50kW in a "Park & Ride" as chances are you're going to be a good few hours!), if you need any help with this then I'll be happy to lend some assistance where I can.
That initially sounds like a good suggestion, and if both TT, might have addressed the 411.3.1.1 requirement. BUT, there are a couple of other considerations. For example, if they are not connected to the same supply transformer, or any of the TT earth electrodes are too close to PME buried earth (or worse, HV!) then you might have an issue with impulses and fault transfer potential.
Which is why there is another fundamental requirement of BS 7671 - 542.1.3.3, which says you need to be very, very careful bonding earths of different installations together, and you take full responsibility for that.
I appreciate that increasing numbers of EV points, or even non-electrified street furniture, mean that the available spaces are disappearing, but what has been done to date? How have you coped so far?
It's incredibly difficult and we are trying to find an electrical solution which reduces or negates the need to be a certain distance from other installations or street furniture, we also have to comply with many other factors as well, such as noise pollution to the adjacent properties, light intrusion if there are windows next to where we want to put them, if there's any underground structures we can't dig through... the list goes on! There's actually a pretty good document which outlines the requirements of EV charging points - http://ukevse.org.uk/resources/procurement-guidance/
Are you responsible for the design or the install only?
I can see the earthing of EVC points being a major headache in a cramped city centre with existing street lighting, CCTV, ANPR, comms cabinets and so on.
I've never been involved in EVC. I was talking to an estates manager this morning that has been instructed to arrange for 500kW of EVC to be installed at their site.
Time for some CPD.
Regards
Parsley
I essentially am part of the install only as the client provides their own charge points which are all pre-built and shipped over, but I'm sure if we can come to an agreement or a redesign then this could change. We install mainly 7kW and 22kW charge points.
500kW of EVC's Is one hell of a lot. I know Tesla have unveiled a 250kW charge point which requires a 1MW transformer to power 4 of them but we simply don't have the infrastructure to cope with that at the moment. I was asked to look at an install elsewhere as someone wanted to know how many 50kW rapid chargers would fit in the car park - long story short, they didn't go with it as it required a new HV supply to a brand new substation for a few charge points which would have been too powerful for the nature of the car park. (you wouldn't really have a 50kW in a "Park & Ride" as chances are you're going to be a good few hours!), if you need any help with this then I'll be happy to lend some assistance where I can.
We're about to take you to the IET registration website. Don't worry though, you'll be sent straight back to the community after completing the registration.
Continue to the IET registration site