Zs measurement on an Off Peak supply.

On an EIC for just metal board changes, one on "On Peak" and one on "Off Peak", what is the current thinking regarding entering Zs for the latter? - using an estimate of (R1 + R2) + Ze or just enter a Limitation, since this is an existing installation ?   


Jaymack
Parents
  • Is there a 24 hour supply from the same origin - if so this can be used to verify the earthing and supply is OK, and get a Zs for the external part. I;d be tempted to do the rest by calculation or dead tests and add it on.
Reply
  • Is there a 24 hour supply from the same origin - if so this can be used to verify the earthing and supply is OK, and get a Zs for the external part. I;d be tempted to do the rest by calculation or dead tests and add it on.