Hi all, what's the best sequence when installing a new TP&N board. 

1) hang on wall and then build. 

2) build and hang on wall

3) none of the above

Hate doing things twice!

Will be installing steel trunking to bring cables into DB and tails from below using steel trunking and 32mm bushes. 


​​​​​​Regards Ts. 


​​​
Parents
  • I am in agreement with the above including Kelly's suggestion ?


    Plan layout

    do any metal work on box

    fit box

    get cables into box

    install the bits and wire up

    Agree that trunking can make it easier especially if any SWA can be terminated on the trunking rather than the box, also makes any future changes easier.
Reply
  • I am in agreement with the above including Kelly's suggestion ?


    Plan layout

    do any metal work on box

    fit box

    get cables into box

    install the bits and wire up

    Agree that trunking can make it easier especially if any SWA can be terminated on the trunking rather than the box, also makes any future changes easier.