Hi all, what's the best sequence when installing a new TP&N board. 

1) hang on wall and then build. 

2) build and hang on wall

3) none of the above

Hate doing things twice!

Will be installing steel trunking to bring cables into DB and tails from below using steel trunking and 32mm bushes. 


​​​​​​Regards Ts. 


​​​
Parents
  • Former Community Member
    0 Former Community Member
    Hi Tatty

    Same tatty that's on the fire forums?? 

    Was going to put steel trunking top and bottom for the reasons you've mentioned along with a intumescent gasket between the board and trunking. 


    What's the point of mounting on strut? I've seen this on plenty of commercial sites can see it being handy for rear entry but that's it have I missed something here?


    ​​​John have already given consideration to spacing between enclosures, but still a very valid point that you bring up. 


    Regards Ts
Reply
  • Former Community Member
    0 Former Community Member
    Hi Tatty

    Same tatty that's on the fire forums?? 

    Was going to put steel trunking top and bottom for the reasons you've mentioned along with a intumescent gasket between the board and trunking. 


    What's the point of mounting on strut? I've seen this on plenty of commercial sites can see it being handy for rear entry but that's it have I missed something here?


    ​​​John have already given consideration to spacing between enclosures, but still a very valid point that you bring up. 