Can I ask your opinion in relation to neutral /earth on this rather untidy changeover arrangement located just downstream of the main isolator? There are 2no 3-pole contractors with mains in bottom left and generator in bottom right. On the stud adjacent they have connected gen neutral, DNO neutral and installation earth. The arrangement means a self-imposed conversion to an unauthorised TNCS. I can’t be sure if the existing supply is already TNCS.
The Electricity Safety, Quality and Continuity Regulations 2002 (ESQCR). ESQCR 2002 apply only to Great Britain. There is a separate legislative framework in Northern Ireland, the Electricity Safety, Quality and Continuity Regulations (Northern Ireland) 2012, that are enforced by HSENI
The Electricity Safety, Quality and Continuity Regulations 2002 (ESQCR). ESQCR 2002 apply only to Great Britain. There is a separate legislative framework in Northern Ireland, the Electricity Safety, Quality and Continuity Regulations (Northern Ireland) 2012, that are enforced by HSENI