This discussion is locked.
You cannot post a reply to this discussion. If you have a question start a new discussion

Failed EICR

Former Community Member
Former Community Member

Hi just want to know what you guys and girls do in the following situation. 

You've carried out an EICR its failed. 

Once the remedials have been carried out do you redo the original EICR so it's Satisfactory?

Or do you fill out minor works certs and give these to the customer along with the original failed report so once cross referenced  it results in being satisfactory. 

This has been bugging me for awhile now. 

Regards TS

Parents
  • You should complete MWCs for the repairs, which are then kept with the EICR. You can’t re-issue the EICR without retesting everything as you don’t know if anything has changed, other than what you have worked on. I doubt you will want to do a free re-test, and I doubt your client will pay for another EICR. 
     

    Regards,

     

    Alan. 

Reply
  • You should complete MWCs for the repairs, which are then kept with the EICR. You can’t re-issue the EICR without retesting everything as you don’t know if anything has changed, other than what you have worked on. I doubt you will want to do a free re-test, and I doubt your client will pay for another EICR. 
     

    Regards,

     

    Alan. 

Children
No Data